MONTECO INSIGHTS: Major Project for Greiner Bio-One GmbH
Success Story & Field Report
The Project: Modernization as Part of a High-Tech Retrofit
The major project at Greiner Bio-One GmbH involved the modernization, or retrofit, of the automated high-bay warehouse. A warehouse management and material flow control system that had been in operation for around 20 years was completely replaced by an integrated, future-oriented SAP LES solution, including a direct conveyor technology interface and a simulation-based material flow controller. In parallel, extensive roof refurbishment and fire protection upgrades were carried out in the warehouse area.
The Challenge: “Open-Heart Surgery”
The conversion work and integration tests had to be carried out during non-working hours at night and over the turn of the year, as the warehouse remained partially active throughout the project. Upon completion of the modernization, the performance of the high-bay warehouse was doubled.
At peak times, up to 70 logistics and installation experts from five different suppliers were working on site simultaneously. Numerous specialist departments worked continuously to keep production stable throughout the entire project duration.
-
InfrastruktInfrastructure & Site Setup:
Independent preparation of the construction site setup plan, covering production, transport and storage facilities, sanitary and break areas, and waste management concepts, as well as the setup and supervision of installation activities in close coordination with Körber’s project management team and the external trades. -
Space & Logistics Management:
Coordination, scheduling and strategic allocation of pre-assembly areas, as well as precise management of all construction-site deliveries. -
Cross-Trade Coordination:
Interface management and operational coordination between the various construction, installation management and commissioning teams from different third-party providers. -
Installation & Commissioning Supervision:
Continuous planning, supervision and monitoring of all mechanical, electrical and IT-related installation activities, including close support during commissioning, partial acceptance and final acceptance. -
Quality Assurance & Documentation:
Complete documentation of all activities in the construction diary, recording of potential construction defects and strict coordination of their rectification. -
Schedule & Safety Controlling:
Ongoing schedule planning, regular construction meetings and progress reporting in coordination with Körber, as well as continuous monitoring of compliance with safety and health regulations in consultation with the construction safety coordination team under the BauKG.
Project Success in Figures
Project Metric / Target
- Optimization of implementation period
- High-bay warehouse performance
- Intralogistics availability
- Production supply
Result & Project Success
- Reduced from 40 to 34 calendar weeks
- Successfully doubled, representing a 100% increase
- Significantly increased and made future-proof
- Fully maintained despite substantial additional logistics requirements